It was important that we captured the first show home with a timelapse that showcases our vision in action. This video demonstrates our commitment and the successful transformation of our ideas into reality.
Majority of a new build is in the labour and building processes over and above the materials, with the Habitat Housing modular sizing and prefab panels, we cut down that time significantly and include the benefits of a sustainable home and reducing waste.
Below, you'll find a series of videos that break down the construction phases, giving you a clear vision of what to expect when you choose Habitat for your new home.
The team at Habitat Housing
WEEK ONE
The build begins with your choice of foundations including Wildboar footings or concrete slab, cassette floor, prefab wall panels, interior framing and trusses install.
WEEK TWO
Roofing and joinery completed which puts the Emerald watertight in just 7 working days!
Cavity batten installed and the start of cladding.
WEEK THREE & FOUR
Interior work had started this week with insulation, GIB and doors while the cladding install finishes up.
WEEK FIVE
Exterior painting completed and scaffold brought down for the next stages.
WEEK SIX & SEVEN
Kitchen, wardrobes and painting the interior. Extension of the Wildboar footings and decking is well underway.
WEEK EIGHT
A week of finishing touches on the 3 bedroom, 2 bathroom, Emerald Showhome, ready to open!